Nicholson Drive Construction Timelines Near Lakes at Harveston

The Nicholson Drive work with a groundbreaking, a budget and a finish year sits at the far end of the drive from Lakes at Harveston, just south of LSU. Closer to the Harveston entrance, a planned roundabout has a council vote behind it and no construction date. The stretch of Nicholson right outside the neighborhood is still in planning, with an estimated bid date of 2030. Taken together, the roadwork on the daily drive north moves in that order, starting at the far end and reaching home last.

Here is where each piece stood as of the most recent public updates, starting at the far end.

Near Brightside, the groundbreaking came before the road work

Officials broke ground on Wednesday, August 12, 2026, on a $28 million MOVEBR project to widen Nicholson Drive from two lanes to four between Gourrier Avenue and Brightside Drive. WAFB reported that the plans include a boulevard with J-turns and shared-use paths on both sides, and that construction is expected to wrap up sometime in 2028.

The work crews have actually been doing since then is preparation. The city-parish's Segment 1 project page says clearing and grubbing started in February 2026. That package removes trees, signs and other obstructions so the utilities can move. It also takes down and rebuilds the fencing along the Kensington, Via Horti and Rue de Grace subdivisions. The September 2026 update expected the package to finish in October. MOVEBR's May 2026 update set the order of what comes next. Roadway construction will be advertised once the utility relocations are complete.

So the August groundbreaking marked the start of a sequence. The lanes, J-turns and paths come in a later contract that hadn't been bid as of the last update.

This month the work shows up more on the sidewalks than in the travel lanes. The northbound sidewalk along the railroad is closed to pedestrians and is expected to reopen after October 23. Work is starting soon on the southbound side at Brightside and Nicholson, where crews will remove trees, fencing and light poles and pour concrete. That sidewalk will close on and off as the work moves.

Saturdays in the fall, the crews step aside

MOVEBR says there is no construction on LSU game days, and crews finish early on the Fridays before home games.

LSU's schedule lists three home games left in 2026:

  1. Mississippi State, Saturday, October 17, at 11 a.m.
  2. Alabama, Saturday, November 7, kickoff time to be announced
  3. Texas, Saturday, November 14, kickoff time to be announced

That puts the early Friday finishes on October 16, November 6 and November 13.

Game-day traffic runs on its own rules. WAFB's October 3 game-day guide says streets around campus switch to contraflow before and after games, police direct the traffic, and there is no set time for contraflow to begin. The 2026 rideshare pickup and drop-off point is Lot 406, across from the LSU Vet Center on Skip Bertman Drive. Once contraflow starts, rideshare drivers who aren't already in that lot can't get onto campus. LSU Athletics posts its 2026 pregame and postgame maps on its parking page, along with a custom Waze map that carries real-time travel information. The exact road-by-road routing changes from season to season, and those maps are the current reference.

The change nearest the Harveston entrance has a vote and no start date

The project that would most directly change how Harveston residents reach Nicholson isn't on Nicholson. It's a roundabout planned for Bluebonnet Boulevard and Harveston Way.

When WAFB covered it in March, the station said the roundabout would connect to the back of University Club. That would give University Club a second way in and out, in place of the single access onto Nicholson residents have now. It would also let people living off Harveston Way reach Nicholson faster. A University Club resident told the station the single entrance causes long lines on weekday mornings.

Metro Councilman Rowdy Gaudet, who has worked on the project for several years, told WAFB the delays came from coordinating with St. George and the developers. The new city will ultimately own the infrastructure. He was also direct about the timing:

"We won't see cones and digging dirt for a little while. We're working towards that, but you've got to get all these contractual arrangements in place, and that's where we're headed now."

The official record since then shows real progress and an unfinished process. On March 11, 2026, the Metro Council adopted Resolution 59280 by a 12-0 vote. It authorizes a cooperative endeavor agreement that puts $1.2 million in traffic-impact fees toward the roundabout. The $1.2 million figure in the headlines is one contribution, not the full cost. The cooperative endeavor agreement estimates the roundabout itself at more than $4.8 million. Under that agreement, SLP Development LLC contracts with the builder and pays the project costs, Burtville Development Corporation cooperates, and Longwood Development I Corporation contributes land.

The latest official update came from St. George's Zoning Commission on April 6, 2026. According to the minutes, the applicant had agreed to include a Harveston Way roundabout but hadn't yet submitted updated plans. The commission recommended the related development-plan change only on conditions, including satisfactory updated traffic and drainage studies and written confirmation from the property owner before the City Council acts. No public record since April announces a contractor, a start date or a completion date.

The roundabout is the project closest to the neighborhood gate, and it's the only one in this story without any published timeline.

The stretch outside Harveston waits behind the campus end

Each of the corridor projects on MOVEBR's list has a published schedule. Between LSU and Harveston, the dates get later the closer the road gets to the neighborhood. Segment 3, south of Gardere, is the only one scheduled later still.

Project Stretch Status as of September 2026 Next published milestone
Nicholson Segment 1 Brightside to Gourrier, near LSU Clearing and grubbing, utility relocation to follow Roadway construction bid after utilities move. Completion expected in 2028
Staring Lane Extension Burbank to Gardere/Nicholson 60% plans complete and under review Estimated advertisement Q2 2027
Nicholson Segment 2 Ben Hur to Bluebonnet Planning, within DOTD's LA 30 environmental review Estimated advertisement 2030
Nicholson Segment 3 Parish line to Gardere Planning, within the same LA 30 review Estimated advertisement 2034

The Staring Lane extension is the nearest of these. It would carry Staring from Burbank to Gardere and Nicholson behind the Traction Sports Complex, and it's being designed by DOTD.

Segment 2 is the one that reaches Bluebonnet, the end of Nicholson nearest the Harveston Way side of the neighborhood. MOVEBR describes it as a proposed widening from Ben Hur to Bluebonnet with a current cost estimate of $64 million. That is more than twice the $28 million Segment 1 near campus. The design study will consider a complete-street cross-section. Once it's built, the road from Ben Hur to Gardere transfers to the city as a parish route, while the section from Gardere to Bluebonnet stays a state route. The September 2026 update says the project moves forward only after DOTD's LA 30 environmental document is approved.

Segment 3, south of Gardere toward the parish line, sits in the same environmental review. Its concept includes a shared-use path on the east side of the road.

The segment near LSU, about to become four lanes with paths on both sides, carries a 2028 finish date. The segment outside Harveston, which costs more, carries a 2030 advertisement date and depends on an environmental review. Advertisement only means bidding opens, and construction comes after that. On current schedules, Harveston residents will drive a finished boulevard near campus for years before the widening reaches their own stretch of Nicholson.

For the rest of this fall, the Nicholson changes near Lakes at Harveston are small and dated. The railroad-side sidewalk near Brightside is set to reopen after October 23, crews stop on the three remaining LSU home Saturdays, and the clearing package was expected to wrap up in October.

At Del Rio Real Estate, we follow the MOVEBR updates, Metro Council minutes and St. George agendas where these Nicholson and Harveston Way decisions get recorded. If you'd like to talk through what the Nicholson and Harveston Way timelines mean for your own plans, we'd welcome the chance to Schedule a Private Consultation.